BAMBOO PILE CONSTRUCTION PROCESS
BAMBOO PILE CONSTRUCTION PROCESS
1. Scope of application of bamboo pile construction measures
Bamboo piles are used to reinforce the ground for constructions with low load transfer or to reinforce the wall of the excavation pit. Driving bamboo piles is to increase the compactness of the soil, reduce the void coefficient, leading to increased bearing capacity of the ground.
Bamboo piles are used in areas that are always wet and flooded. If bamboo piles work in wet soil, their lifespan will be quite high (50-60 years or longer). If bamboo piles work in dry or erratically wet soil, the piles will rot very quickly.
Bamboo piles should only be driven in flooded soil so that the bamboo does not rot. If driven in dry soil without water, the bamboo will rot, which will have the opposite effect of weakening the ground.
Do not drive bamboo piles in sandy soil because sandy soil cannot retain water. Usually, bamboo piles are only driven in clay soil with water.
How far apart is enough to drive bamboo piles? Normally, people drive 16-25 piles/m2 because they are easy to divide (pile spacing 20-25 cm). Thicker than that, it probably cannot be driven.
Currently, there is no specific calculation theory, but we can do the following: in the design phase, assume that after driving bamboo piles, the ground reaches a certain tightness (through the void ratio), from which the bearing capacity of the ground can be calculated, using that as the basis for foundation design (or we can assume the bearing capacity of the ground after driving piles).
After driving piles, re-test to check the bearing capacity of the ground. If it is not much different from the assumed bearing capacity, there is no need to modify the design (in reality, there are few testing experiments, but they are mainly based on experience).
2. Pile requirements

Đóng cọc tre bằng gầu máy
3. Pile driving method
There are 2 basic methods of pile driving when implementing bamboo pile driving construction measures as follows:
4. Pile lowering diagram
If it is a pile clump or a pile field to reinforce the ground, then drive from the middle outwards. If it is a pile strip or a row of piles, drive in sequential rows. For piles to reinforce the wall of the excavated hole, drive from the row of piles farthest from the edge of the excavated hole inwards. In Hanoi and some neighboring provinces; bamboo pile construction is usually done in the following order:
Result: The adjacent houses are built and used but there are no cracks or tilts. In some cases, due to poor construction or other reasons, there may also be subsidence (although very little).
So placing the foundation of the project directly on the top of the bamboo piles of cajuput is probably good. As for using loose materials (sand, stone), it is likely that only the increased strength due to the effect of compacting the soil of the bamboo piles of cajuput piles can be used.
5. Techniques to know when constructing bamboo piles
With the current measures and procedures for constructing bamboo piles; ensuring the construction techniques must be sure to clearly understand the technical requirements below; to complete the process of constructing bamboo piles in actual construction.

Cọc tre sau khi hoàn thành quy trình đóng cọc
Follow and ensure the above technical requirements; you have completed the bamboo pile construction process accurately and most commonly.
6. Introducing a reputable design & construction consulting service provider
The importance of construction units is undeniable, their reputation will ensure the quality and aesthetics of your project. Currently, there are many units providing design and construction services to meet the increasing construction needs in our country. Therefore, finding a reputable unit is not easy and requires you to spend time researching. In the selection process, you need to research carefully and ensure that the accompanying unit must have high expertise, many years of experience, have a clearly signed contract, transparent costs, ... To help customers save time searching, Hung Nghiep Phu Construction Investment Co., Ltd. is confident that it will be the best choice for you.

Hung Nghiep Phu Construction Investment Co., Ltd. with the mission of providing the best solutions and services, building a prosperous community with customers, Hung Nghiep Phu is gradually affirming its brand through sincere cooperation, with a leadership team with ethical capacity, creativity, high expertise and strategic vision. Hung Nghiep Phu owns a team of skilled, highly qualified employees who will bring customers the best quality technology.
Hung Nghiep Phu Construction Investment Co., Ltd. - specializes in constructing civil and industrial works. We look forward to accompanying customers in construction projects as well as continuous procedures such as planning diagrams, applying for construction permits, completing procedures, applying for fire prevention and fighting certificates, ... If you have any questions or are in need of design, completing procedures, please contact us immediately for free consultation!
>>> See more:
_____________________
CONTACT INFO:
Facebook: Công ty TNHH Đầu tư Xây dựng Hưng Nghiệp Phú (興業富)
Hotline: 1800.3368 (Miễn phí)
Website: xaydunghunnghiepphu.com
Gmail: kinhdoanh01@xaydunghungnghiepphu.com
Address: No. 2034D, Group 22, Phuoc Thai Quarter, Thai Hoa Ward, Tan Uyen City, Binh Duong Province
------
Source: Compiled from the Internet